               continuously studied, the financial security cost of MFSP Liabilities are not expected to decrease


               in value. Hence, financial securities amount to billions of dollars in the near future.

                        Figure 3.Reclamation and Disturbance by Companies, December 31, 2011







































                                           Source: Provided by Alberta Environment


                     2. Financial securities

                                                      2.1.  Financial Security Calculation Period

                     According to Alberta Environment MFSP Guide security is calculated annually. If current


               MFSP Assets are lower than previous MFSP Assets or current MFSP Liabilities are higher than

               previous year MFSP Liabilities then security required will increase in the current period. In other

               words, required financial security will increase because less reclamation has been done than the


               Planned Reclamation. If current MFSP Assets are higher than previous MFSP Assets or current

               MFSP Liabilities are lower than previous MFSP Liabilities then less security will be provided in